|

|
| Las Vegas Wins with
Concrete Pressure Pipe |
| |
|
Lake
Mead, approximately 50 miles from Las Vegas, Nevada, is the main
source of fresh water to Las Vegas Valley, and one of the world’s
largest subaqueous pressure pipelines was installed under Lake Mead’s
Boulder Harbor. The original intake structure, Intake No 1, which
was built by the Bureau of Reclamation, and the associated water
supply system, has been supplying water to the Valley since the
early 1960’s. The demand for water in Las Vegas has been growing
due to tourism expansion and 7% annual residential growth rate.
To meet the increased water supply demand, the Southern Nevada Water
Authority (SNWA) has embarked on a 2 billion dollars capital improvement
plan to expand the existing 400-mgd water supply system. The expansion
includes the Lake Mead Intake No. 2 Project, which runs parallel
to the original intake.
|
|
The 144-inch diameter, 3600-ft. long Reinforced Concrete Cylinder
Pipe (RCCP) subaqueous pipeline, the Bay Aqueduct, is part of SNWA’s
Lake Mead Intake No. 2 Project. The Bay Aqueduct was designed for
a nominal flow of 600 mgd with a peak flow of 800 mgd, an internal
pressure of 160 psi under normal conditions, an extreme pressure
of 300 psi, 80 ft. of external water head and up to 20 feet of soil
cover at the banks. This 144- inch diameter RCCP Bay Aqueduct, which
runs from Saddle Island to the mainland under Lake Mead’s Boulder
Harbor, may be the largest subaqueous water pressure pipeline in
the world. CH2M Hill engineers designed the 144-inch diameter RCCP
Bay Aqueduct. Because of the demanding design and installation conditions,
CH2M Hill and SNWA have only considered the rigid wall RCCP option
for this project. Ameron International’s Water Transmission Group,
manufactured the RCCP at its plant in Rancho Cucamonga, California.
Lake Mead Constructors (LMC) installed the subaqueous pipeline.
|
| Special Design Leads to Unique Installation |
The
144-inch diameter RCCP was designed in conformance with the AWWA C300
standard and the AWWA M9 Manual with modifications to meet project
requirements. The RCCP included the following special features:
- A 5/8 inch thick steel cylinder.
- A deep double gasketed joint to allow for testing and settlement
after installation and dewatering. The joint was designed for
a joint lap of 6.5 inches to allow for a minimum straight pull
of 2.5 inches and a minimum joint deflection of 1.5 inches.
- Each cylinder and joint ring assembly were hydrostatically tested
to 160 psi in the plant.
- Three reinforcing cages, an inside cage in the concrete lining,
an intermediate cage over the steel cylinder, and an outer cage.
- A 12-inch thick concrete wall with 6000 psi strength.
- Manufactured and shipped in 16.67-ft. standard lengths weighing
60 tons per section.
- LMC joined three pipe sections together on shore to form 50-ft.
long assemblies weighing 180 tons per assembly.
- A special corrugated grout bands to allow for grouting the
exterior joint space from inside the pipe after dewatering.
- An internal welded butt-strap restraint system installed after
dewatering..
- Special color markings in the joint and exterior spring lines
of the pipe to establish the limits of the joint stab and backfill
limit for the divers during installation.
- Precast concrete saddles for placing over the pipe after backfilling
up to the springline to counteract buoyancy after dewatering.
|
| Proof of Design Test |
Since the Bay Aqueduct is one of the most critical elements
of the new Intake No. 2 Project, qualification testing was required
before full-scale production began. Ameron manufactured three 9-ft.
long pipe sections in conformance to the project requirements to conduct
the structural and hydrostatic joint testing.
|
|
Hydrostatic
Joint Tests: Two test pipe sections were assembled in the plant
with a controlled inside joint gap of 3.75 inches (1.25 inch joint
gap in the fully inserted position) to allow a straight 2.5 inch
pull. The spigot of the assembled joint had two grooves and two
gaskets, which allowed testing between the gaskets through two 1/4
inch tapped holes 180 degrees apart. A water hose and a pressure
gauge were connected to the bottom test hole and a connection and
bleed valve was connected to the top test hole. The system was pressurized
to 45 psi for 10 minutes with no pressure drop. A portable “power
pac” was used to adjust the joint gap. The test was repeated with
a 1.25-inch gap on onside and a 2.75-inch gap on the other side
for a total deflection of 1.5 inches. The system was pressurized
for 8 minutes with no pressure drop. The joint was deflected in
additional 1/2-inch increments until the joint leaked when the gasket
disengaged from the bell on one side. The total joint deflection
was 3 inches before the joint leaked. The hydrostatic joint testing
results verified that the specification requirements of a minimum
2 1/2-inch straight pull and a minimum of 1 1/2-inch deflection
were met and exceeded.
Structural Testing: The purpose of the structural testing was to
verify the structural and radial tension performance of the pipe.
Two test pipe sections were each instrumented with two horizontal
and two vertical deflection monitors. In addition, a radial tension
monitor was installed at the invert near the bell. The test pipe
was positioned in the D-load (3-edge bearing) machine, which is
equipped with two hydraulic jacks that press the head beam against
the pipe. A data logger was connected to the deflection and radial
tension monitors and a pressure transducer was connected to the
hydraulic pressure system of the jacks. The data logger would instantaneously
measure the transducer pressure and corresponding applied load and
the vertical and horizontal deflection and radial tension movements
of the pipe. Load/deflection curves indicate that the deflection
is in the elastic range up to a load of 20 kips/ft. The 0.01-inch
crack was observed at a load of 21 kips/ft.
The
maximum load which could be applied was 27.5 kips/ft. The apparent
radial tension movements up to a load of 20 kips/ft were negligible.
The radial tension crack was observed at a load of approximately
20 kips/ft. The theoretical D-load capacity for the test pipe was
15 kips/ft. Although the 3-edge bearing load (D-load) is a very
severe loading condition, the structural tests have verified that
the proposed 144-inch RCCP can safely withstand the design loads
and validated the design assumptions.
Grout Band Tests: Two of the test pipe sections were assembled
and used to test the proposed corrugated steel grout band and gasket
assembly. A total of eight trial tests were conducted until the
design of the grout band and grout-pumping procedure was finalized
and approved. This is the first time for this type of grout band
application.
Precast Concrete Saddle Fit Up Test: The test pipe sections were
used to check and verify installation. Lake Mead Constructors (LMC)
installed the Bay Aqueduct in over 80 feet of water with both soil
and rock trenching and bedding preparation completed ahead of pipe
installation. LMC joined three pipe sections together on land to
form 50-ft. long assemblies. The assemblies, with temporary bulkheads
attached at both ends, were rolled over by means of a cable and
winch set-up to the launch way saddles, and then the assembly was
launched through a rail and cable system on a ramp to the water.
The assemblies were floated and pulled with a tug to the laying
barge.
The pipe assembly was picked up with a hoisting frame with one
of the bulkheads removed and lowered into place. The joints were
pulled together by pumping water out through the remaining bulkhead
to form a vacuum that eased the joint to its final position. The
joints were tested during installation and grout bands placed into
position. The backfilling was placed up to the pipe springline,
at which point large precast concrete saddles were placed over the
pipe to counteract buoyancy, and backfilling was completed. After
dewatering the line, the exterior joint space was grouted from the
interior of the pipe through small grouting nozzles. Interior steel
butt-straps were welded across the joint for restraint and shotcrete
reinforced with wire mesh was applied over the interior surface
of the butt-strap to fill the interior joint spaces.
Bay Aqueduct Completion
The installation and successful testing of the RCCP Bay Aqueduct
was completed in December of 1999. The pipeline was hydrostatically
tested at 220- psi pressure. This rugged RCCP subaqueous pipeline
met the challenge of very difficult installation conditions. The
design and construction versatility of concrete pressure pipe is
demonstrated on the Southern Nevada Water Project. Whether it’s
a subaqueous line, a tunnel, or a downtown main, concrete pressure
pipe can meet your needs.
|
|
top
|