Los Vaqueros Water Supply Project

Ameron International delivered 16 miles of Reinforced Concrete Cylinder Pipe (RCCP) to supply water to thirsty Californians in the San Francisco Bay area. Known as the Los Vaqueros Water Supply Project, it consisted of a new dam and a 100,000 acre-foot reservoir, two pumping plants and a total of 104,000 feet of large diameter pipeline.

The project had been under study for a number of years with a major concern being the potential for discovery of prehistoric archaeological sites. According to "Archaeological and Geoarchaeological Investigations of the Los Vaqueros Project Area," by Jack Meyer and Jeff Rosenthal, after fifteen years of negotiations and effort, test excavations for the Los Vaqueros Archaeological Project began in 1994. In all, testing was conducted at nine prehistoric archaeological sites located near the proposed dam or within the flood pool of the reservoir. Five of the sites required limited testing. However, the other four required extensive archaeological excavations with some surface deposits associated with late prehistoric occupations, but three sites contained deep buried deposits that dated to 1,000 or more years old. Archaeological excavations revealed the presence of numerous artifacts, several intact features, and over 150 prehistoric Native American burials. Ameron supplied nearly 16 miles of 78 to 96-inch diameter Reinforced Concrete Cylinder Pipe for the Los Vaqueros Reservoir Project in Northern California.

Some of the artifacts recovered from the deeper deposit included a wide stemmed obsidian projectile point, hand stones, and milling slabs. Preliminary evaluation suggested that they were 6,000 to 8,000 years of age, and may therefore represent some of the oldest cultural materials discovered so far in the San Francisco Bay Region.

With a strong archaeological program underway, the project owner, the Contra Costa Water District, awarded the pipeline contract to ARB, Inc., of Brentwood, California, and issued the notice to proceed in November 1994. The first major water supply project in California for over 20 years, the reservoir will provide a new source of drinking water for nearly a half-million residents.

Briefly, the intake pump station, the Old River Pumping Plant, lifts water from the Sacramento/San Joaquin Delta into 34,000 feet of 78-inch diameter pipeline and then to a transfer reservoir. The transfer reservoir provides hydraulic grade control for the system and serves as the intake for the second pumping plant.

That plant discharges to 24,000 feet of 72-inch diameter pipeline, which in turn delivers water to Los Vaqueros Reservoir. A third pipeline, which consists of 28,000 feet of 90-inch diameter and 19,000 feet of 96-inch diameter pipe, feeds the Contra Costa Canal from either the Old River Pumping Plant or the Los Vaqueros Reservoir.

ARB chose the rigid AWWA Standard C300, Reinforced Concrete Pressure Pipe, Steel-Cylinder Type (RCCP) for the 78inch, 90-inch and 96-inch diameter pipelines over the flexible pipe alternative. The pipe supply contract was awarded to Ameron, which supplied the pipe from its Tracy, California, plant, located close to the project site. Selection of rigid Reinforced Concrete Cylinder Pipe (RCCP) resulted in substantially reduced costs to the owner since the supporting strength of the soil was poor and substantial over-excavation would have been required to provide for the high levels of compaction needed to support steel pipe.

The design pressure for the 78-inch, 90-inch and 96-inch pipeline varied from 50 psi to 175 psi, and earth cover loads varied from 8 feet up to 40 feet. ARB did much of its excavation on a 3/4 to 1 slope. Scrapers were used to remove the first 4 to 5 feet and then an excavator to complete the trench. Pipe bedding was a 6-inch layer of pea gravel.

The design requirements were stringent and required two processes to fabricate the pipe cylinders, and three processes to fabricate the reinforcing cages. The principal features of the RCCP for the project were:

  • A welded steel cylinder with joint rings welded to its ends, and with cylinder thickness varying from 0.1046 inch up to 0.25 inch. The steel spigot had two grooves for two gaskets in order to have a testable joint.
  • Continuous reinforcing bar was wrapped helically over the cylinder for the inner steel when the diameter of the bar was up to 1/2 inch.
  • An outer reinforcing cage was included when the bar diameter increased from 1/2 inch up to 3/4 inch.

he pipe wall, consisting of dense concrete, encased the steel cylinder and inside and outside reinforcing cages. The required wall thicknesses were:

Diameter, in. Wall Thickness, in.
78 7 1/2 and 11
90 8 1/2 to 10 1/4 & 15
96 9 and 12 1/2

The mobilization for the project was a major undertaking due to the required design parameters. Ameron cast the first pipe in early March 1995, and completed the casting operation for the standard pipe in January 1996.

The double gasket, testable joint allowed every joint to be air tested during installation. Hydraulic thrust in the pipeline was resisted by field welding a sufficient number of joints adjacent to the thrust point.

Montgomery Watson, Walnut Creek, California, was the engineering consultant for the District on the Los Vaqueros water supply project.

top