Northridge Water District Partners With Other Agencies
 

Northridge Water District (NWD), located in the north central part of Sacramento County, in Sacramento, California, along with several other area water agencies faced the similar issue of finding an adequate water supply for a growing population through conjunctive use of surface and ground water.

Northridge draws on 33 wells in its district to supply 19,145 customers of which 17,238 are residential. Over the past 20 years, the ground water table has been overdrafted at a rate of 1.5 to 2 feet per year. The lower water table deteriorated the water quality as well as increased the energy costs for pumping. In addition, state and federal environmental agencies are instituting new water quality standards that would require further expenditures for the 33 wells.

The District has historically relied solely upon groundwater, however, Northridge has been trying for 20 years to get access to surface water. To pursue a jointly built pipeline would offer many advantages such as combined engineering design, environmental studies, bond sales, pipeline construction, etc.

In December of 1993, Northridge partnered with the San Juan Water Group to build a project known as the Cooperative Transmission Pipeline. The project allows more water to flow from Granite Bay into the North Sacramento area, and the pipeline can be tapped along the way as necessary. A water treatment plant on Folsom Lake would supply water to Northridge through a joint water agencies pipeline. Northridge would then complete an 8.5-mile conveyance pipeline along Antelope Road for its portion of the joint project.

In the spring of 1994, Northridge sought bids for supplying 8,275 ft. of 48-inch pipe due to the County of Sacramento widening Antelope Road. A supply bid was taken because of the critical completion schedule for the road widening. Ameron International was awarded the contract to supply 48-inch AWWA Standard C303, Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type in 40-foot laying lengths.

After the completion of the road-widening project, Northridge negotiated with Ameron for the supply of 6,275 ft. of 48-inch Concrete Pressure Pipe on Schedule A of the conveyance pipeline. The district required that this portion be installed in the winter to reduce construction impact on the residential area. Pipe laying in predominately city streets complicated the project's public relations.

While Schedule A was being completed, Ameron and Northridge again negotiated for the balance of the conveyance pipeline, Schedules B through F. Northridge awarded the supply contract in December of 1995 for 25,950 ft. of 48-inch, 725 ft. of 36inch, and 3,975 ft. of 30-inch Concrete Pressure Pipe. The relationship that developed between Ameron and Northridge was evident by the trust in working together to complete the final portion of the conveyance pipeline.

Schedules B through F involved many demanding tasks such as an 800 feet long bore under Interstate 80, a major interstate highway connecting California and Nevada, and 125 feet long bore under a primary Southern Pacific Railroad line. Also, those schedules required multiple installation crews in order to meet the anticipated completion date. Portions of the 48-inch pipe were installed in quite residential streets therefore requiring minimal disturbance for the citizens.

Boyle Engineering was the design engineer for the conveyance pipeline as well as the joint water agencies pipeline. T & S Construction of Sacramento was the installation contractor on the entire water conveyance pipeline. Ameron International supplied 45,200 ft. of 48, 36, and 30-inch Concrete Pressure Pipe for Northridge's pipeline.

Each agency could have approached its problems individually. It was working together that succeeded in providing an upgraded water supply to a growing population. The pipeline also allows Northridge to participate in the conjunctive use program of Sacramento County, which is designed to stabilize ground water overdraft in the area by the year 2000. Northridge Water District has sought and attained the best possible water available for their customers. This was truly an investment for their future.

top