 |
| Trunk Sewer Line Involves Combination
of Open Trench and Underground Drives |
| |
|
PCL
Civil Constructors Inc., San Diego, Calif., currently is constructing
approximately five miles of the Rose Canyon Trunk Sewer in San Diego,
Calif., under a $23.8 million contract with the City of San Diego.
The line is a combination of open-cut sections and six underground
drives. The underground drives, which account for one-sixth
of the total length, are required because in several areas the line
passes under Caltrans or railroad right-of-way property where an
open cut is not possible. In several other areas the depth
of the new sewer pipeline, as much as 45 feet, makes an open-cut
trench impractical, according to Rick Selensky, resident engineer
for the City of San Diego.
|
|

Of the 24,000 feet of pipeline, 20,000 feet is
open-cut with an average depth of 16 feet. The work is confined
within a specific corridor to protect the environment in Rose Canyon.
This corridor will be revegetated at the end of the project.
The Ameron reinforced concrete pipe ranged in inside-diameter size
from 48 inches to 60 inches, with all of the pipe made with PVC
lining. A ring of PVC is welded to seal the joints afer the
pipe is in place.
One of the challenging aspects of
this project is making the live tie-ins to the existing sewer using
temporary bypasses, explains PCL Project Manager Mike McKinney.
There are existing 18-in.-diameter and 33-in.-diameter sewer
lines in the project area that are already at near-capacity. In
one of the open-cut areas a section of the 18-in. line must be removed
to make room for the new, larger pipe. This will involve a
temporary bypass to shift the 18-in. pipe volume into the 33-in.
pipeline. Since this is a combined sanitary sewer and strom
drain, this portion of the work is scheduled for after the end of
the wet season to avoid the chances of a spill. Concrete Contractors
Interstate, San Diego, Calif., is handling the concrete tie-in structures.
Westcom Microtunneling, Pleasant
Grove, Utah, which is handling the six underground drive sections
as a subcontractor to PCL, is using a Lovat tunnel boring machine
(TBM) in conjenction with a pipe jacking system. seventeen shafts,
37 feet long and 14 feet wide, were eccavated to provide jacking
pits and receiving pits. PCL excavated the pits while Anderson
Drilling, Lakeside, Calif., installed the soldier beams and lagging
to shore the walls. Trebor trench boxes were used for shoring
in the shallower pits. PCL lowered either a backhoe or a mini-excavator
into the deeper pits to load out a muck bucket.
The TBM sits on the front joint of
pipe and advances as additional joints are jacked forward in five-foot
increments. The unit overcuts the tunnel by only one inch for the
86-in.-outside-diameter pipe. A double O-ring gasket system
prevents the bentonie slurry from escaping into the jacking shaft.
The jacking equipment generates 1,200 tons of force to advance
the pipe.
|
|
A muck train rides on tracks placed within
the pipe and hauls a 1-1/2 -cu.-yd. muck tub back from the rear
of the TBM to the pit, where a crane hoists it out for off-site
disposal. Carpet has been placed under the tracks to protect
the PVC lining of the pipe.
Each 86-in.-outside-diameter joint
of pipe is 20 feet long, has eight-in.-thick walls and weighs 53,000
lbs. The pipe is being manufactured at Ameron's Rancho Cucamonga,
Calif., facility, 2-1/2 hours away by truck. The joints are
hauled to the site and stored temporarily on specially modified
trailers. As the joints are needed, PCL moves the trailers
adjacent to the pits, where the railroad tracks are placed inside
prior to eac joint being lowered into the jacking frame.
The two longest underground drives are 1,600
feet long and utilize midpoint pits to reduce the jacking length.
The remaining four drives will average just under 200 feet
long. A tunnel laser is being used for guidance of the TBM.
Other key members of the PCL team
in addition to McKinney are General Superintendant Dale Jones and
Project Engineer Chris Stack.
|
|
top
|