 |
| Large Capacity Water Main Prepared
The City of Roseville For Growth |
| |
|
The city planners of Roseville, California were looking forward
to an economically prosperous future. Their city's population was
expected to reach 103,000 by the year 2010. This repre-sents an
increase of nearly 90 percent. New residents are drawn to the area
by its clean air, lifestyle, and convenient location in the rolling
foothills of the Sierra Nevada mountains, about 20 miles northeast
of the state capital, Sacramento.
Not content to simply "let" progress happen, Roseville had initiated
a master plan for putting necessary infrastructure in place to accommodate
surging population growth and the changing nature of the businesses
that contribute to its tax base. The city expects to spend over
$100 million on water facility improvements alone from 1990 to 2010.
|
| |
|
Clean
Water is an Area Attraction
Like many growing cities across America, Roseville has seen
its industrial base change over the years. Once the largest
railroad-switching yard west of the Mississippi and a thriving
agricultural community, Roseville has moved with the time,
successfully attracting expanding companies in high technology
and service industries. Two new hospitals were built in the
area, and the Del Webb Corporation selected Roseville for
its first western non-desert planned retirement community.
Construction on the 1,200-acre development is complete. Sun
City Roseville has approximately 3,500 homes, plus a 27-hole
golf course.
Water quality is one of the region's key drawing cards. Roseville
gets its water from the American River, which flows from its
origins above Lake Tahoe in the Sierra Nevada mountains into
Folsom Lake. Quality water, in addition to an abundance of
affordable land, its relatively earthquake-free setting, and
easy access to transportation made Roseville a very attractive
setting for high technology businesses. A 66-in Prestressed
Concrete Cylinder Pipe being lowered into trench and placed
onto prepared crushed rock bedding.
|
Its high technology firms are major water users. The city's two
largest employers are Hewlett-Packard, which built its first computer
products plant located outside California's Silicon Valley in 1979,
and NEC Electronics which makes microchips in a 650,000 sq. ft.
facility opened in 1986. Together these two companies employ more
than 5,400 people. Both have plans to add more jobs and manufacturing
space in Roseville.
NEC, in particular, requires extremely clean, particulate-free
water for semiconductor fabrication. The company uses more than
one million gallons of water a day in its chip man-ufacturing facility.
Other companies are coming as well, with AT&T being the latest high
technology firm to move into the area.
Planning for Growth
Roseville's water needs required that a new 66" diameter pipeline
supplement the existing 42" AWWA Standard, C303 Bar Wrapped Concrete
Cylinder Pipe (CCP), supplied by Ameron in 1969. Helmick & Lerner
of Sacramento was retained by the City to design a system with 11,490
LF of 66" AWWA Standard, C301 Prestressed Concrete Cylinder Pipe
(PCCP) to bring water from Roseville's Water Treatment Plant (WTP).
Paralleling the existing line and sharing the same easement, the
new pipeline will serve as a backup for the existing pipe and supply
water from the WTP that was expanded from 24 to 48 MGD.
On January 31, 1994, T & S Construction Company, the successful
bidder selected Ameron, to supply the specified PCCP. T & S Construction
is a local family-owned and operated company that specializes in
pipelaying jobs throughout the region. When the project was completed
in the summer of 1995, the pipelines now have a capacity of 96 MGD.
Roseville estimates peak daily water demands for 2010 will be a
maximum of 62 MGD.
|
|
Prestressed
Concrete Cylinder Pipe chosen for its Strength
The City's facilities engineer characterized the pipeline project
as fairly straightforward, except for its proximity to the existing
42" CCP carrying the city's only water supply. Giant underground
granite boulders had to be excavated and blasted without disturbing
the old system, which is only 10 feet away.
Those circumstances, plus the pipeline's location just outside
the city limits and travel-ing through pasture lands that were yielding
to housing development, led project engineers to choose PCCP for
both its rigidity and its strength. The 66-inch pipe, in standard
24-ft lengths was tested to 150 psi after the installation was completed.
The pipe was bedded in crushed rock and the contractor backfilled
with a minimum three-foot cover. A PCCP section after joint assembly.
The line made one creek crossing that required restoration of plant
life. There were four tie-ins - one at each end of the line and
two more located at approximately the halfway point. Because the
tie-ins were with pipe that had already been in the ground up to
25 years, T & S Construction paid special attention to testing their
integrity.
The excavation skirted a new residential neighborhood adjacent
to the site where a new high school was built. To accommodate the
developer of an upscale housing tract, the pipeline contractor started
digging in the middle of the project. Trenching and pipelaying moved
toward the city. When that phase was completed, the contractor returned
to the middle point and moved toward the treatment plant.
T & S
Construction's founder, the late Tom Spinella, showed his willingness
to approach the project in this way, which reflected his strong
sense of community, and confidence in the suitability of PCCP for
the job. Tom had worked with many types of pipe since he start-ed
in business 44 years ago. "Concrete pipe is tough," he said. "It's
easy to join and seal, and its longer lengths make the job go quicker.
Besides, those people in their new houses wouldn't want us tearing
up their brand new streets if we don't have to!"
The protective characteristics of the pipe's mortar coating were
another factor in the choice of PCCP. Its manufacture and design,
including its standard single O-ring Carnegie joints, complied with
the standards approved by the American Water Works Association (AWWA
C301-92 and C304-92) for Prestressed Concrete Cylinder Pipe.
When their new PCCP pipeline was placed in service, Roseville expected
to be well prepared for the demands of the next century. Roseville
residents are living the old adage of the West - prosperity and
a plentiful supply of water go hand-in-hand. A 24-ft pipe section
being prepared for joint assembly
|
|
top
|